The first pile has been driven, marking the official start of the construction of our new factory. Each strike of the hammer not only lays a physical foundation, but also a solid base for innovation, sustainability, and efficient production.
Behind this symbolic first pile is the upcoming installation of approximately 900 piles, each to an average depth of 15 meters, which will support the main structural framework. In addition, approximately 17,000 piles will be cast in place, averaging 10 meters deep, to create a solid foundation for our concrete floor. Together, we are building a sustainable future in the manufacturing industry